06 - Energy sufficient office building in Leiden, Netherlands |
|
Project
name
|
'Rijnlandshuis':
Head office of Water Board 'Rijnland'
|
| |
 |
Keywords
|
Demonstration
in durable and energy sufficient building including an optimal working
climate. Situated in the Bio Science Park in Leiden, The Netherlands
|
Start
of project
|
Realized
in 1999
|
End
of project
|
In
operation
|
Contact
person
|
Hoogheemraadschap van Rijnland
Sector Building Management
Postbus 156, 2300 AD Leiden
Phone: 0031-71-3063063
Email:
This e-mail address is being protected from spam bots, you need JavaScript enabled to view it
(re: sector building management)
|
Short
project description / project function
|
The
Water Board Rijnland in the Netherlands needed a new head office. In this
office there is room for 360 people and the building is designed for:
optimization of the working climate, sustainable building and low energy
consumption.
Total area of working space of the building 12'000 m2. There is
also a separate plumbing for toilet water and storage of cold and warm water
in the subsoil. http://www.rijnland.net.
On another site full details can be found (in Dutch language) about energy, waste disposal,
materials which have been used: http://www.dubocentrum.nl/projecten/project.php?reclD=31&item=samenvatting
|
Summary
of experiences
|
People
who work in the building are quite pleased with it. 70 % of the working time
people can work in daylight which saves energy. Light from outside and the
light of the electric lamps are reflected to get a equal distribution of the
light in the rooms; workers are becoming less tired.
|
Project
benefits
|
Lower
energy consumption, less water consumption and the building can be easily
taken apart and the individual construction parts can be easily reused. Per
year 200 tons of CO2 are saved by the innovative energy system which is also cost
effective (50'000 Euro savings on energy costs).
An
energy storage was built using the underground (60 m deep pipes) of the
building site Water
use in toilet is 15 liter per person, which amounts to saving about 1.4
milion liters of drinking water per
year, due to the use of rainwater or surface water.
|
Project
level
|
Mature
technology: All the available new technologies for a sustainable office are
implemented in this building.
|
Financial
scale
|
Building
costs: 18'500'000 Euro (inclusive 11,5 % extra cost for sustainable building
activities and materials).
Maintenance
costs/year: 80'000 Euro
|
Environmental
conditions
|
Leiden,
Netherlands. River delta, sea climate
|
Altitude
|
Height
above sea level: at sea level
|
Description
of special local conditions
|
A
little outside the centre of Leiden
|
Why
is this ecological engineering
|
In
this building a lot of available technologies in the field of water savings,
energy savings and sustainable construction of the building has been
implemented to create a more sustainable building.
|
|
|
Last Updated ( Tuesday, 18 December 2007 )
|